Keep the shuttles flying? It’ll cost you

$5 billion for extension to 2012, but $11 billion for 2015, NASA says

Image: Space shuttle
Attached to a diesel-powered tractor, the space shuttle Endeavour is towed back to its hangar on Dec. 13 for post-mission processing.
Jack Pfaller / NASA
  Interactive

A look at the timeline for construction of the International Space Station

INTERACTIVE
Shuttle history
Trace every flight of America's space fleet
Slideshow
  Month in Space
See moonshadows on Saturn's rings, volcanoes on Earth and Mars and other out-of-this-world imagery from June 2009.

more photos

By Becky Iannotta
Space News staff writer
updated 9:09 p.m. ET Jan. 6, 2009

WASHINGTON - NASA could extend space shuttle operations to 2012 by adding three flights — at a cost of roughly $5 billion — without dramatically affecting the agency's plan to return astronauts to the moon by 2020, according to a draft internal report on delaying the planned 2010 retirement of the orbiter fleet.

However, extending shuttle operations to 2015, when a replacement system is slated to become available, would cost more than $11 billion and have severe impacts on lunar exploration hardware development, according to the draft report, prepared by a team at NASA's Johnson Space Center in Houston.

Both scenarios assume that the additional funding needed to keep the shuttle flying does not come out of the budgets for developing the replacement system, consisting of the Orion crew capsule and its shuttle-derived Ares 1 launcher. Both vehicles are being developed under the Constellation program, which encompasses the hardware NASA needs to transport astronauts to and from the international space station after the shuttle retires, and later to the moon.

Story continues below ↓
advertisement | your ad here

NASA Administrator Mike Griffin ordered the study in August amid increased concerns over the five-year gap between the shuttle's retirement and the debut of Orion and Ares 1. NASA's plan to rely exclusively on Russian Soyuz vehicles to launch astronauts during that period came under heavy criticism following Russia's August invasion of neighboring Georgia.

In a Dec. 15 interview, Griffin called reliance on Soyuz "unfortunate in the extreme," but said NASA needs the $3 billion it spends annually on shuttle to move ahead with the replacement system.

"Every time I have spoken about [the gap] I've laid it at the feet of budget," Griffin said. He emphasized that without an increase in NASA's overall budget, extending shuttle operations will result in a corresponding delay for Orion-Ares 1.

The shuttle extension study began two months before NASA kicked off another study of other options for closing the five-year gap. In October, a team from the NASA Engineering and Safety Center at Langley Research Center in Hampton, Va., began assessing whether NASA could accelerate development of Ares 1 and Orion. NASA officials have said Ares 1 and Orion will begin space station missions in March 2015, although they have set an internal deadline of September 2014 and are under pressure to further reduce the gap.

The internal assessments will be compared and finalized before being released sometime in January, Doug Cooke, NASA associate administrator for exploration systems, told reporters during a Dec. 17 teleconference.

"The study we did on acceleration didn't assume the shuttle extension, so we've got to get to a resolution on all of that," said Cooke, who declined to discuss details of a Dec. 15 briefing on the acceleration study. "We need to understand that all together."

Weighing cost and added risk
The shuttle draft report, a copy of which was obtained by Space News, evaluates the implications of the two- and five-year extension scenarios for their costs, work force implications and impacts on the Constellation program.

According to the study, both options increase the risk of losing a crew or vehicle: The two-year extension increases the cumulative risk from a 1-in-8 probability to 1 in 6; extending operations through 2015 increases the risk to 1 in 4. The risk of losing an orbiter or crew on any given mission is 1 in 77, the report said.

A decision on whether to pursue either extension option is needed by May 2009 to reverse plans to draw down shuttle operations, the draft report said.

A two-year shuttle extension offers limited benefits but does not carry significant technical risk. It does not eliminate the gap or solve work-force retention issues, but would benefit the space station and provide an opportunity to use the shuttle to test Constellation hardware. Examples include Orion's thermal protection system and docking system, the draft report said.

Contract extensions of up to 24 months would be required for hardware such as the space shuttle onboard computer, robotics, camera system, reusable solid rocket motor, main engines and external tanks.

While there would be no need to produce new shuttle external tanks under the 2012 option, extending related activities at NASA's Michoud Assembly Facility in New Orleans could delay modifications of the facility needed to begin producing the Ares 1 upper stage. That, in turn, could delay the start of Ares 1 upper stage production by 12 months, the draft report said, adding that NASA is developing mitigation plans.