Skip navigation

Cost for nuclear waste site jumps to $90 billion

Long-delayed Yucca Mountain earlier estimated at $58 billion

Image: Tunnel into Yucca
Part of the proposed Yucca Mountain repository has already been built, including this rail line and tunnel deep into the Nevada mountain.
Joe Cavaretta / AP file
Video: Environment  
Drought and sandstorms, Iraq's latest battle      
July 14: A devastating drought has left Iraq bone dry. Swaths of farm land have turned to baked dirt, drinking water supplies are threatened and to add to the misery, a massive dust storm has blanketed the country. NBC's Steve Wende reports. 

Environment slide shows  
  
California's Fertile Central Valley Suffers From Statewide Drought
Getty Images
Calif. farm areas drying up
California’s farming areas aren’t dust bowls, at least not yet, but a three-year drought and water restrictions have slashed crops and jobs, undermining rural communities.

Text alerts on msnbc.com

Breaking news alerts (about 1 per day)
Click here to sign up or text NEWS to MSNBC (67622).

Find more alerts at alerts.msnbc.com

updated 3:14 p.m. ET July 15, 2008

WASHINGTON - Turns out, it's going to cost taxpayers $32 billion more than first thought to open and operate the nation's first nuclear waste dump.

The Bush administration's latest calculation — made public Tuesday — is that the facility will cost over $90 billion. It's the first official estimate since 2001, when the figure was $58 billion.

Ward Sproat, the Energy Department official in charge of managing the controversial Yucca Mountain repository project in Nevada, disclosed the new number to reporters after a congressional hearing Tuesday.

Story continues below ↓
advertisement | your ad here

The estimate includes $9 billion already spent and covers about 100 years of operation until the dump, 90 miles northwest of Las Vegas, is sealed up forever.

Some of the increase is due to inflation, Sproat said. Also Energy Department officials now expect the dump will hold more radioactive waste than the 77,000 tons initially approved by Congress.

Report due out in a few weeks
A report with precise cost breakdowns will be released to Congress in the next several weeks, Sproat said.

Already, some 64,000 tons of radioactive spent fuel rods are stored at commercial reactor sites in 33 states, according to the Nuclear Energy Institute. Most of it is stored in vault-like pools while some has been moved into dry-cask storage, where Nevada lawmakers, who oppose Yucca Mountain, would like it to stay.

Sproat opposes that plan as impractical. He also objected to other interim storage options raised Tuesday by frustrated lawmakers, who reported hearing from constituents about the need for new energy sources.

Commercial nuclear power plants now produce some 20 percent of U.S. electricity, but concern about waste disposal has hampered the industry's growth.

Yucca Mountain was originally supposed to open in 1998 but has been beset by lawsuits and political and scientific controversies. The best-possible opening date is now 2020, Sproat told lawmakers at an Energy and Commerce subcommittee hearing.

Even that is contingent on a steady money stream, something that Senate Majority Leader Harry Reid, D-Nev., has blocked.

The Energy Department did succeed in submitting a required construction license application to the Nuclear Regulatory Commission last month. The commission has up to four years to decide whether to approve it — but that timeline, too, is dependent on congressionally approved budgets.

Copyright 2008 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

Sponsored LinksGet listed here
Online College Courses
Boost your career with an online Degree. Pick from Leading Colleges!
www.EarnMyDegree.com

Sponsored links

Resource guide