Human error cited in Fla. power failure

Report: Engineer disabled 2 levels of system’s protection; 1 million affected

Video: Life  
Chestnut takes hot dog eating title
July 4: The gastronomically-blessed California native beat archrival Takeru Kobayashi by gobbling down a world record 68 franks in 10 minutes. NBC’s Lester Holt reports.

Text alerts on msnbc.com

Breaking news alerts (about 1 per day)
Click here to sign up or text NEWS to MSNBC (67622).

Find more alerts at alerts.msnbc.com

  Photo features  
  More
Image:
AP
  Week in Pictures
Prayers for rain, street battles in Honduras and Michael Jackson's last dance are among this week's memorable pictures from around the globe.
Image: Michael Jackson
AP
PhotoBlog
View and discuss the pictures and issues that caught our eyes.
updated 12:22 p.m. ET March 1, 2008

MIAMI - A power failure that plunged large parts of Florida into the dark earlier this week was caused primarily by human error, the state's largest electric company said Friday.

Florida Power & Light issued a preliminary report saying that a field engineer was to blame for Tuesday's failure, which affected more than 584,000 customers, or the equivalent of more than 1 million people.

The engineer was investigating a malfunctioning switch at one of the power company's substations in west Miami when he disabled two levels of protection for the system, officials said.

Story continues below ↓
advertisement | your ad here

While he was making measurements of the switch, a circuit shorted, making a loud noise and smoke that was reported as a fire. Normally, the protection system would have contained the consequences of the short circuit, but because both levels of protection had been removed, the problem cascaded to other parts of the system.

In total, 26 of the company's 435 transmission lines and 38 of its 600 substations were affected. Two nuclear reactors and a natural gas unit at Turkey Point south of Miami shut down protectively. Two other FPL plants were also affected.

"We don't know, still, why that particular employee took it upon himself to disable both sets of relays," FPL president Armando Olivera told reporters.

The employee, who had "significant tenure," has been put on paid leave during an investigation, Olivera said. It would have been appropriate for the employee to disable one, but not two, levels of protection while making measurements, he said.

A full investigation could take months, Olivera said.

Copyright 2008 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.